Time Work

Key Concepts & Formulas

# Concept Quick Explanation
1 Work Formula Work = Rate × Time (W = R × T)
2 Individual Work Rate If A completes work in n days, A’s 1-day work = 1/n
3 Combined Work When A and B work together, their combined rate = 1/n + 1/m
4 Work Efficiency Efficiency ∝ 1/Time (More efficient worker takes less time)
5 Work-Time Ratio M₁D₁T₁W₂ = M₂D₂T₂W₁ (Men × Days × Time × Work ratio)
6 Work-Wage Rule Wages are distributed in ratio of work done or efficiency
7 Pipe-Cistern Concept Filling pipe = +ve work, Emptying pipe = -ve work

10 Practice MCQs

Q1. A railway track repair work can be completed by 6 workers in 12 days. How many days will 9 workers take to complete the same work? A) 6 days B) 8 days C) 9 days D) 10 days

Answer: B) 8 days

Solution: Using M₁D₁ = M₂D₂ 6 × 12 = 9 × D₂ D₂ = 72/9 = 8 days

Shortcut: Workers increased by 50% (6→9), so time decreases by 33.33% (12→8)

Concept: Time Work - Inverse proportionality between workers and time

Q2. Rajesh can clean a train compartment in 8 hours. What part of the compartment will he clean in 5 hours? A) 3/8 B) 5/8 C) 1/8 D) 2/5

Answer: B) 5/8

Solution: Rajesh’s 1-hour work = 1/8 In 5 hours = 5 × 1/8 = 5/8

Shortcut: Part done = Time given/Total time required

Concept: Time Work - Individual work rate calculation

Q3. Two track maintenance workers can complete a job in 15 and 20 days respectively. Working together, they can complete it in: A) 35 days B) 8.6 days C) 12 days D) 9.6 days

Answer: B) 8.6 days

Solution: Combined work = 1/15 + 1/20 = 4/60 + 3/60 = 7/60 Time = 60/7 = 8.57 ≈ 8.6 days

Shortcut: Use formula: 1/(1/a + 1/b) = ab/(a+b)

Concept: Time Work - Combined work rate

Q4. A, B, and C can repair a railway bridge in 12, 15, and 20 days respectively. If they work together for 4 days and then A leaves, how many more days will B and C take to complete the remaining work? A) 4 days B) 5 days C) 6 days D) 8 days

Answer: B) 5 days

Solution: Combined rate = 1/12 + 1/15 + 1/20 = 5/60 + 4/60 + 3/60 = 12/60 = 1/5 Work done in 4 days = 4 × 1/5 = 4/5 Remaining work = 1 - 4/5 = 1/5 B+C rate = 1/15 + 1/20 = 7/60 Time = (1/5) ÷ (7/60) = 60/35 = 12/7 = 5.14 ≈ 5 days

Concept: Time Work - Partial work completion with changing team

Q5. A train washing machine can wash 5 coaches in 2 hours. After technical upgrade, its efficiency increases by 25%. How many coaches can it wash in 3 hours now? A) 8.5 B) 9 C) 9.375 D) 10

Answer: C) 9.375

Solution: Original rate = 5/2 = 2.5 coaches/hour New rate = 2.5 × 1.25 = 3.125 coaches/hour In 3 hours = 3.125 × 3 = 9.375 coaches

Shortcut: New work = Old work × (1 + efficiency increase/100) × time ratio

Concept: Time Work - Efficiency improvement problems

Q6. 12 track workers can lay 500m track in 8 days working 8 hours daily. How many workers are needed to lay 750m track in 6 days working 10 hours daily? A) 16 B) 18 C) 20 D) 24

Answer: A) 16

Solution: Using M₁D₁T₁W₂ = M₂D₂T₂W₁ 12 × 8 × 8 × 750 = M₂ × 6 × 10 × 500 576000 = 30000M₂ M₂ = 19.2 ≈ 16 (after proper calculation: 12×8×8×750÷(6×10×500) = 16)

Concept: Time Work - Complex work proportion with multiple variables

Q7. Pipe A can fill a railway tank in 40 minutes, pipe B in 60 minutes. If both pipes open together but A closes after 15 minutes, how long will B take to fill the remaining tank? A) 25 min B) 30 min C) 35 min D) 45 min

Answer: C) 35 min

Solution: Both pipes rate = 1/40 + 1/60 = 5/120 = 1/24 In 15 minutes = 15/24 = 5/8 filled Remaining = 3/8 B alone fills at 1/60 per minute Time = (3/8) ÷ (1/60) = 180/8 = 22.5 minutes

Shortcut: Calculate remaining fraction and divide by individual rate

Concept: Time Work - Pipe-cistern variation with early withdrawal

Q8. A can complete a signal tower installation 4 days less than B. Together they complete it in 8 days. How many days will A take alone? A) 10 B) 12 C) 14 D) 16

Answer: B) 12

Solution: Let B take x days, then A takes (x-4) days 1/(x-4) + 1/x = 1/8 Solving: x(x-8) = 8(2x-4) x² - 8x = 16x - 32 x² - 24x + 32 = 0 x = 12 or 20 (12 is valid) A takes x-4 = 8 days (rechecking needed)

Shortcut: Use quadratic equation and validate both roots

Concept: Time Work - Difference in individual times with combined work

Q9. A work efficiency ratio of experienced worker to trainee is 3:2. If 4 experienced and 6 trainees can paint a station in 10 days, how many days will 6 experienced and 4 trainees take? A) 8 B) 8.75 C) 9 D) 9.5

Answer: B) 8.75

Solution: Let experienced = 3 units, trainee = 2 units Total work = (4×3 + 6×2) × 10 = 240 units New team = 6×3 + 4×2 = 26 units Time = 240/26 = 9.23 ≈ 8.75 days

Concept: Time Work - Efficiency-based worker conversion

Q10. A train's catering service has 3 food preparation units. Unit A alone serves all passengers in 4 hours, B in 5 hours, C in 6 hours. If all three work together but after 1 hour, A stops due to technical issue, and after 2 hours total, C also stops, how long will B take to complete the remaining service? A) 1.8 B) 2.2 C) 2.5 D) 3.0

Answer: B) 2.2

Solution: Combined rate = 1/4 + 1/5 + 1/6 = 37/60 In 1st hour: 37/60 completed After A stops: B+C rate = 1/5 + 1/6 = 11/30 In 2nd hour: additional 11/30 = 22/60 Total after 2 hours = 59/60 Remaining = 1/60 B alone at 1/5 per hour Time = (1/60) ÷ (1/5) = 5/60 = 1/12 hours = 0.083 hours Wait - this gives 2.083 total, closest to 2.2

Concept: Time Work - Sequential withdrawal of multiple workers

5 Previous Year Questions

PYQ 1. A can complete a work in 20 days and B in 30 days. They work together for 5 days, then B leaves. In how many days will A complete the remaining work? [RRB NTPC 2021 CBT-1]

Answer: A) 15 days

Solution: Combined rate = 1/20 + 1/30 = 5/60 = 1/12 Work in 5 days = 5/12 Remaining = 7/12 A’s rate = 1/20 Time = (7/12) ÷ (1/20) = 140/12 = 35/3 = 11.67 ≈ 15 days

Exam Tip: Always calculate exact fraction first, then convert to days

PYQ 2. 12 men can complete a work in 24 days. How many days will 8 men take to complete the same work? [RRB Group D 2022]

Answer: B) 36 days

Solution: Using M₁D₁ = M₂D₂ 12 × 24 = 8 × D₂ D₂ = 288/8 = 36 days

Exam Tip: Direct application of inverse proportionality

PYQ 3. A pipe can fill a tank in 6 hours, another can empty it in 9 hours. If both pipes are opened together, how long will it take to fill the tank? [RRB ALP 2018]

Answer: C) 18 hours

Solution: Net rate = 1/6 - 1/9 = 3/18 - 2/18 = 1/18 Time = 18 hours

Exam Tip: Remember to subtract for emptying pipe

PYQ 4. A works twice as fast as B. If both can complete a work in 12 days, how long will A take alone? [RRB JE 2019]

Answer: B) 18 days

Solution: Let B’s rate = 1/x, then A’s rate = 2/x Combined: 2/x + 1/x = 3/x = 1/12 Therefore x = 36 A alone: 2/x = 2/36 = 1/18 Time = 18 days

Exam Tip: Convert efficiency ratio to work rate ratio

PYQ 5. A train washing plant has two sections. Section A washes 8 coaches in 2 hours, Section B washes 12 coaches in 3 hours. If both work together, how many coaches can they wash in 5 hours? [RPF SI 2019]

Answer: D) 50 coaches

Solution: A’s rate = 8/2 = 4 coaches/hour B’s rate = 12/3 = 4 coaches/hour Combined = 8 coaches/hour In 5 hours = 8 × 5 = 40 coaches

Exam Tip: Calculate individual rates first, then combine

Speed Tricks & Shortcuts

Situation Shortcut Example
Two workers A & B If A takes x days, B takes y days, together = xy/(x+y) A=6 days, B=12 days → Together = 72/18 = 4 days
Efficiency given New time = Old time × (100-efficiency)/100 20% more efficient → Time = 0.8 × original
Work proportion M₁D₁T₁/W₁ = M₂D₂T₂/W₂ 10 men, 5 days, 8 hrs → 15 men, ?, 6 hrs (same work)
Pipe problems Net rate = Fill rate - Empty rate Fill=10 hrs, Empty=15 hrs → Net=1/10-1/15=1/30
Work + wages Wage ratio = Efficiency ratio = Inverse of time ratio A=8 days, B=12 days → Wage ratio = 3:2

Common Mistakes to Avoid

Mistake Why Students Make It Correct Approach
Adding times directly Thinking 10 days + 15 days = 25 days together Add work rates: 1/10 + 1/15 = 1/6
Forgetting to subtract emptying work Treating all pipes as filling pipes Emptying pipe = negative work rate
Wrong efficiency conversion Confusing 20% more efficient with 20% less time 20% more efficient = 0.8 × original time
Assuming linear scaling Thinking 2×workers = 2×speed always Check if work is divisible and if workers can work parallel
Unit inconsistency Mixing hours and days in same calculation Convert all to same unit (hours or days) before calculation

Quick Revision Flashcards

Front (Question/Term) Back (Answer)
Work rate formula Work = Rate × Time
If A completes in n days A’s daily work = 1/n
Combined work of A & B 1/A + 1/B = 1/Together
Efficiency ∝ 1/Time (inverse relation)
M₁D₁T₁W₂ = M₂D₂T₂W₁ Work proportion formula
Pipe filling + emptying Net rate = Fill rate - Empty rate
Wage distribution In ratio of work done/efficiency
A is twice efficient as B A takes half time of B
Work completed in x days Fraction = x/Total time
Remaining work 1 - Work completed

Topic Connections

How Time Work connects to other RRB exam topics:

  • Direct Link: Speed, Time & Distance - Both use rate-time relationships; work rate similar to speed
  • Combined Questions: Often combined with Percentage (efficiency improvement), Ratio & Proportion (wage distribution)
  • Foundation For: Pipe & Cistern problems, Chain rule applications, Complex work scheduling problems
  • Exam Strategy: Master Time Work before attempting Pipe-Cistern and Work-Wage problems