Question: 16 men can complete a piece of work in 8 days. In how many days can 12 men complete the same piece of work?
Options:
A) 10
B) $ 9\frac{1}{3} $
C) $ 10\frac{2}{3} $
D) Cannot be determined
Show Answer
Answer:
Correct Answer: D
Solution:
- 16 men can do a work in = 8 days 1 man can do a work in $ =8\times 16 $ days 12 men can do a work in $ =\frac{8\times 16}{12} $ days $ =10\frac{2}{3} $ days